Eisenhüttenstadt sewage plant

Technical data / process stages

  • Inlet buffer
  • Hydrolysis container
  • Anaerobic reactors
  • Degasification / carbon removal
  • Sludge activation
  • Final sedimentation
  • Sludge thickening / drainage
  • Chemicals dosing
  • biological/chemical gas purification
  • Desulfurization by activated carbon
  • Gas tank
  • 2 x gas torches
  • Block heat and power plants 3 x 1,000 kWel

Scope of supply and service

  • Turn-key construction
  • Procedural design
  • Complete detailed design for construction, mechanical and electrical engineering

Highlights

  • Compressed air generation with magnetic field suspended turbo compressor
  • The WWTP has an electrical power requirement of approx. 1,200 kW and generates hourly a capacity of 3.000 kW, i.e. the grid is supplied with a considerable spillover

WWTP Eisenhüttenstadt
(PDF, English)
387 kB
Client
Trinkwasser- und Abwasserzweckverband Oderaue
Start of works
10/2008
Completion
02/2010