Eisenhüttenstadt sewage plant
Technical data / process stages
- Inlet buffer
- Hydrolysis container
- Anaerobic reactors
- Degasification / carbon removal
- Sludge activation
- Final sedimentation
- Sludge thickening / drainage
- Chemicals dosing
- biological/chemical gas purification
- Desulfurization by activated carbon
- Gas tank
- 2 x gas torches
- Block heat and power plants 3 x 1,000 kWel
Scope of supply and service
- Turn-key construction
- Procedural design
- Complete detailed design for construction, mechanical and electrical engineering
Highlights
- Compressed air generation with magnetic field suspended turbo compressor
- The WWTP has an electrical power requirement of approx. 1,200 kW and generates hourly a capacity of 3.000 kW, i.e. the grid is supplied with a considerable spillover
- Client
- Trinkwasser- und Abwasserzweckverband Oderaue
- Start of works
- 10/2008
- Completion
- 02/2010