North Gaza Emergency Sewage Treatment

Technical data

  • Approx. 350.000 PE
  • Inlet flow 35.000 m³/day
  • Activated sludge process
  • Inlet pumping station
  • Primary sedimentation
  • Aeration basins
  • Final sedimentation
  • Sludge thickening
  • Digestion
  • Sludge dewatering
  • Conditioning by lime

Scope of supply and service

  • Turn-key erection
  • STULZ-PLANAQUA is the leading partner of a Joint Venture established with a local civil contractor
  • Engineering and design of the entire plant
  • Delivery and Installation of mechanical and electrical equipment
  • Commissioning

Kläranlage Nord Gaza
(PDF, German)
231 kB

WWTP North Gaza
(PDF, English)
236 kB
Client
Palestinian Water Authority
Financing
World Bank
Start of works
June 2010
Completion
Scheduled end of 2013